A.
City
Notice of Development Application – Issuance and Contents. The
city zoning administrator shall provide a notice of development application
to the public and the departments and agencies with jurisdiction as
provided in this section. If the responsible official has made a determination
of significance under Chapter 43.21C RCW concurrently with the notice
of development application, the notice of development application
shall be combined with the determination of significance and scoping
notice. Nothing in this section prevents a determination of significance
and scoping notice from being issued prior to the notice of development
application. The notice shall include but not be limited to the following:
1.
The
name of the applicant.
2.
Date
of application.
3.
The
date of the notice of completeness.
4.
The
date of the notice of development application.
5.
The
location of the project, including legal description and common address
or location.
6.
A
project description.
7.
A
list of the project permits included in the application and, if applicable,
a list of any studies requested under RCW 36.70B.070 or 36.70B.090.
8.
A
list of any other requested approvals, actions, and/or required studies
and the identification of other permits not included in the application,
to the extent known by the city.
9.
A
public comment period not less than 14 days nor more than 30 days
following the date of notice of application, and statements of the
right of any person to comment on the application, receive notice
of and participate in any hearings, request a copy of the decision
once made, and any appeal rights.
10.
Identification of existing environmental documents and the location
where such documents can be reviewed.
11.
A city staff contact person and phone number.
12.
The date, time, place and type of a public hearing if applicable
and one has been scheduled.
13.
A statement of the preliminary determination, if one has been made at the time of notice, of those development regulations that will be used for project mitigation and of consistency as provided in Chapter 18.08 SLMC.
14.
A statement that the decision on the application will be made within
120 days of the date of the notice of completeness.
15.
Any other information determined appropriate by the city, such as
the city's threshold determination, if complete at the time of issuance
of the notice of application.
B.
Time
Frame for Issuance of Notice of Application.
1.
The city shall issue a notice of development application within 14 days of issuing a notice of completeness under Chapter 18.05 SLMC.
2.
If
any open record pre-decision hearing is required for the requested
development permit(s), the notice of development application shall
be provided at least 15 days prior to the open-record hearing.
C.
Published
Notice. The notice of development application shall be published once
in the city's official newspaper.
D.
Posting.
Posting of property for site-specific developments shall consist of
one or more notice boards as follows:
1.
A
single notice board shall be placed by the applicant:
a.
At the midpoint of the site street frontage or as otherwise directed
by the city for maximum visibility;
b.
Five feet inside the property line, except when the board is structurally
attached to an existing building; provided, that no notice board shall
be placed more than five feet from the street property without approval
of the city;
c.
So that the top of the notice board is between seven to nine feet
above grade; and
d.
Where it is completely visible to pedestrians.
4.
Removal
of the notice board prior to the end of the notice period may be cause
for discontinuance of the city review until the notice board is replaced
and remains in place for the specified time period.
5.
An affidavit of posting shall be submitted to the city by the applicant prior to the hearing or final comment date. If the affidavits are not filed as required, any scheduled hearing or date by which the public may comment on the application will be postponed in order to allow compliance with this notice requirement. Any time required to ensure compliance with this requirement shall be excepted from the 120 days pursuant to SLMC § 18.09.090.
6.
Notice
boards shall be constructed and installed in accordance with specifications
promulgated by the city.
E.
Categorically/Exempt
Projects. A notice of application shall not be required for development
applications that are categorically exempt under Chapter 43.21C RCW
unless a public comment period or an open record predecision hearing
is required.
(Ord. 1079 § 1, 2008)