In all areas of special flood hazards the following provisions
are required for all new construction and substantial improvements:
(1)
All
new construction or substantial improvements shall be designed (or
modified) and adequately anchored to prevent flotation, collapse or
lateral movement of the structure resulting from hydrodynamic and
hydrostatic loads, including the effects of buoyancy;
(2)
All
new construction or substantial improvements shall be constructed
by methods and practices that minimize flood damage;
(3)
All
new construction or substantial improvements shall be constructed
with materials resistant to flood damage;
(4)
All
new construction or substantial improvements shall be constructed
with electrical, heating, ventilation, plumbing, and air conditioning
equipment and other service facilities that are designed and/or located
so as to prevent water from entering or accumulating within the components
during conditions of flooding;
(5)
All
new and replacement water supply systems shall be designed to minimize
or eliminate infiltration of floodwaters into the system;
(6)
New
and replacement sanitary sewage systems shall be designed to minimize
or eliminate infiltration of floodwaters into the system and discharge
from the systems into floodwaters; and
(7)
On-site
waste disposal systems shall be located to avoid impairment to them
or contamination from them during flooding.
(Ordinance 2011-024, sec. 3, adopted 7/25/11; 1988 Code, sec. 13-17)